JES were tasked with the job to combat a condensation problem over a very precise piece of machinery at a paper mill for a valued client. This all had to be completed while the plant was live and under a stringent maintenance plan. We had to manufacture, Inspect, protective coat and install 2No Damper roof vents to an existing roof. This meant opening the existing roof, securing the damper to the existing concrete roof purlins, and then making the roof watertight once again. This was planned around scheduled maintenance, as well as weather constraints with lifting and having the roof open for a prolonged period. All was completed in allotted time and to Budget.